The facade is 70,2% complete.
Roof installation on the residences is nearing completion.
Installations are 83,4% ready.
Shell and core fit out of the residences is 90,3% complete.
Overall readiness of the buildings of urban villas is 58,2%.
Completion of the five-star hotel: 68,4%.
Overall readiness of the conference hall building is 66,8%.
Construction of a free-standing restaurant has begun.