Progress of construction works at Mantera Seaview residence

Overall readiness of residences is 77,3%

Walls and partition walls are 91,3% complete.
67% of the facade has been insulated. Roof installation is nearing completion.
Installations are 84,7% ready.
Completion of shell and core fit out: 88,2%.
Final finishing is being carried out. Walls are being put up, roofs and installations are being mounted, shell and core fit out is being carried out in urban villas.
Overall readiness of urban villas is 50%.
Completion of five-star hotel: 66,3%.
Glazing is 83% complete.
Completion of roof installation: 73,5%.
Shell and core fit out is being carried out.
The conference hall is being constructed.
Completion of the building: 65,8%.