Progress of construction works at Mantera Seaview residence

Overall readiness of buildings of residences is 77%

We ensure fast pace of MANTERA Seaview residence construction.
Walls and partition walls are 90% complete.
97% of the roof is ready.
Installations are 84% ready.  
Completion of shell and core fit out: 87%.
Final finishing is being carried out.
Walls are being put up, roofs and installations are being mounted, shell and core fit out is being carried out in urban villas.
Completion of the five-star hotel: 66%.
Completion of glazing: 83%.
Completion of the roof: 73%.
The five-star hotel is being constructed.
Completion of the building: 65%.