Progress of construction works at Mantera Seaview residence

Overall readiness of buildings of residences is 76,3%

Walls and partition walls are 89,4% complete. 62,3% of the facade has been insulated. Roof installation is nearing completion. Installations are 84% ready.
Shell and core fit out is 85,6% complete.
Final finishing is being carried out.
Walls are being put up, roofs and installations are being mounted, shell and core fit out is being carried out in urban villas. Overall readiness of urban villas is 48,7%.
Completion of the five-star hotel: 65,3%.
Glazing is 81% complete.
Progress in roof installation: 73%.
The conference hall is being built.
Completion of the building: 64%.