The buildings of residences are 74% complete, and works on the construction of walls and partition walls, facade insulation, installation of utility services continue, shell and core fit out is being carried out.
At the same time, construction workers are mounting roofs and installations, carrying out shell and core fit out in the buildings of urban villas.
Glazing of the five-star hotel building is 78,5% complete.
The roof is 73% ready, while utility services are 62% complete.
The conference hall is 60% complete.
Here partition walls and the roof are being constructed and shell and core fit out is being carried out.