Progress of construction works at Mantera Seaview residence

Overall readiness of the residences is 75%

Review of the progress in construction of the deluxe-class complex MANTERA Seaview residence.
Walls and partition walls are 87% complete.
Installations and shell and core fit out are 83% ready.
Completion of final finishing: 8%.
Overall readiness of the five-star hotel building is 64%.
Glazing is 78% complete.
Completion of the roof: 73%.
Completion of utility services: 64%.
Overall readiness of the conference hall is 61%.
Completion of the roof: 80%.
Glazing is 100% complete.
Roofs and utility services are being mounted in urban villas.