Progress of construction works at Mantera Seaview residence

Overall readiness of the residences is 73%

The installation of the roof is complete. Installations in the buildings are 80,5% complete.
Shell and core fit out is 75,8% ready.
Walls have been laid in urban villas, mounting of the roof and installations have begun.
Internal and partition walls are 27,1% ready.
Overall readiness of the five-star hotel is 61,6%.
Glazing is 76,6% complete.
Roof installation is 72,7% ready.
Roof installation on the conference hall building is 80% complete.
Glazing of the conference hall is 91,2% ready.